Before
Where Production Scheduling Reached Its Limits
Manual planning and scheduling relying on Excel and experience
Limited capability to model production reality
No optimal sequencing or process synchronization
Long lead times and high inventory levels
Growing complexity: high vertical integration and expanding product portfolio
AFTER
What Changed
Fully automated production planning and scheduling with APS software
Realistic, transparent modeling of production
Realistic sequencing, synchronized processes
Reliable scheduling across capacity, materials, and skills
Shorter project lead times, lower inventory
Reliable schedules, even when conditions change
Three times the output compared with before implementation
Through sequencing, our overall throughput has increased a lot. Ultimately, that means we get three times the output compared to before the implementation.
GEBHARDT INTRALOGISTICS GROUP
From Experience to Synchronized Production Planning and Scheduling
Gebhardt’s high level of vertical integration shapes its production environment. As its product portfolio expanded and the number of projects increased, planning and scheduling production became increasingly complex. Excel and experience no longer sufficed to reliably synchronize production, assembly, capacity, and material availability. Today, Gebhardt automates production planning and scheduling with Asprova. The APS system realistically models complex production processes and generates reliable sequences. The result: shorter lead times, lower inventory, greater planning and scheduling reliability, and around three times the output.
GEBHARDT INTRALOGISTICS GROUP
Gebhardt Intralogistics Group: System Solutions for Intralogistics
Based in Sinsheim, Germany, Gebhardt Intralogistics Group develops and produces system solutions for internal logistics. The company provides products, software, and services for warehousing, conveying and sorting technology as well as transport and assembly systems. Its solutions are used wherever material flows need to be automated. The portfolio ranges from storage technology, shuttle systems, warehouse robotics, and storage and retrieval machines to conveying, transport and sorting systems, goods lifts, automated guided vehicles, logistics software, and turnkey logistics centers.
One of Gebhardt’s key strengths is its ability to deliver end-to-end automation solutions from a single source—planned, manufactured, and implemented for complex intralogistics processes. A key factor behind this is the company’s high level of vertical integration. Many components are produced in-house and pass through numerous process steps: from laser cutting, punching, and bending to turning, milling, and welding, followed by pre-assembly, final assembly, and electrical installation. External process steps such as galvanizing and painting are also involved.
THE STARTING POINT
When Gebhardt’s Strength Became a Planning and Scheduling Challenge
Gebhardt’s high level of vertical integration is a major advantage for its customers; but it also adds complexity to production planning and scheduling. As the product portfolio grew and more projects and customer orders ran in parallel, keeping production and assembly synchronized became increasingly difficult. Components had to arrive in the right place at the right time across a growing number of interdependent processes.
Until 2016, Gebhardt largely relied on manual production planning and scheduling despite using SAP, with Excel and the production managers’ experience at the core of the process. They set start dates based on experience and reprioritized them at short notice whenever changes occurred. As long as complexity remained manageable, this approach worked. But as the company grew, it became a bottleneck: every additional project, variant, and dependency increased the effort required to review schedules manually, reprioritize them, and make ongoing adjustments.
The existing planning and scheduling approach could no longer reliably model the complexity of Gebhardt’s production environment. Components were not consistently synchronized across production, creating waiting times between process steps. Semi-finished goods remained in inventory longer and lead times increased. At the same time, it became increasingly difficult to provide reliable completion dates for individual customer orders.
For Gebhardt, this was about more than replacing one software tool with another. The priority was to capture the realities of production accurately and turn them into reliable schedules across all projects.