Danwood S.A.

Poland

Buildings and Construction

Before

Customer‘s Challenges

Multiple schedulers relying on Excel

Scheduling limited to key work areas

Difficulty in synchronizing processes and making forecasts

Mismatch between scheduling and actual workload

After

Results with Asprova

One scheduler, 30 minutes daily

Scheduling across all processes and production areas

Accurate forecasts on production and delivery

Reduced inventory through better synchronization

Kamil Malinowski, Fertigungssteuerer
Zitat
With Asprova we could extend scheduling to all jobs and operations; we are able to calculate scheduled operation times much more accurately, and we benefit from reduced WIP and overall inventory.

Kamil Malinowski, Production Control Specialist

ABOUT THE COLLABORATION

Danwood x Asprova

Danwood is one of the largest producers of turn-key prefabricated wooden houses in Europe with a production capacity of 2,000 houses per year.

Before Implementation

Before Asprova APS was introduced, production at Danwood’s two plants in Poland was scheduled by multiple specialists using Excel, and only the work areas most important to the overall production process were considered. Production times were calculated using simplified methods, which often didn’t reflect the actual workload. Synchronizing processes and predicting production times was challenging.

Improvements with Asprova

Since 2018, Asprova APS has been used to schedule all production processes, from material procurement to processing, finishing touches, and truck loading. Scheduling was extended to cover all production areas and operations, incorporating far more data for sequence scheduling, which allows production times for all processes to be calculated down to the minute. Asprova APS schedules 20,000 operations daily. The production schedule is now more flexible and synchronized, resulting in lower levels of semi-finished goods and inventory.

Asprova APS is integrated with MS Dynamics 365 and an MES from EQ System. Scheduling all processes across both plants only takes 30 minutes each day.